top of page
Writer's pictureParveen Arora

SC’s Order On Laying Underground Power Transmission Lines In GIB Habitats In Gujarat and Rajasthan

- Parveen Arora and Suruchi Kotoky


There has been a recent development regarding laying of power transmission lines, which will affect all power producers and projects under construction. In a public interest litigation, the Supreme Court of India has passed an order on April 19, 2021 mandating existing and new power transmission lines to be laid underground, subject to feasibility, in some ecologically sensitive habitats housing endangered species such as the Great Indian Bustard, in the states of Rajasthan and Gujarat.


We have summarised the key directions and the impact of the Supreme Court’s order for developers.



Comments


bottom of page